March has certainly been an interesting month! Like so many construction sites around Wellington, we too have experienced the challenges of labour resourcing due to Covid19 isolation requirements, with on some days over half the builders and trades being in isolation.
This will see some delays in completion and we are working through this with our contractor to confirm updated completion dates – in what is a very fluid environment.
On a positive note, it was exciting to see the start of the CLT second floor installations get under way, and March's site progress highlights are listed for you below:
Stage 1:
All ground floor slabs have now been poured.
9 of 11 of the level 1 slabs have also been poured.
Envelope carpentry (external timber framing) and CLT second floor installation is underway.
Installation of stairs starts next week.
Roofing material will be onsite next week.
Stage 2:
For stage 2b, precast panel installation and primary steel is 90% complete.
For stage 2b, under-slab services (such as sewer, stormwater and water pipes) are due to start this week.
For stage 2c, precast panel installation will start in the next few week's.
The stage 2 CLT panels are in production.
Our construction partner (Aoraki Construction) will be loading regular project updates onto their website here but in the interim, a selection of images from around the site are below:
Stage 1 external framing installed
Stage 1: CLT Floor and Level 1 slab installed
Stage 1: CLT flooring installed