Update on staged programme and estimated completion dates.
Well, it's sure been a busy period behind the scenes for Aro! We've obtained our 'prior to construction' consent conditions for our Resource Consent and the building consents for civil works have been lodged with Wellington City Council also. We are aiming for building consent to be received by the end of April.
Which stage your unit is in:
The construction of Aro has been programmed in stages, which are noted below against individual terrace numbering for ease of reference:
- Stage 1 = Terraces 51 - 61.
- Stage 2 = Terraces 6 - 21 and 32 - 45.
- Stage 3 = Terraces 1 - 5, 22 - 31 and 46 - 50.
- Stage 4 = Apartmento.
Estimated starts for each stage:
Estimated start dates for each stage are noted below:
- Civils: Early May
- Stage 1: 07/07/21
- Stage 2: 18/08/21
- Stage 3: 21/10/21
- Stage 4: 10/09/21
Estimated dates of completion for each stage:
Estimated dates of completion for each stage have been programmed as:
- Stage 1: 04/04/22
- Stage 2: 17/10/22
- Stage 3: 11/11/22
- Stage 4: 01/02/23
As always, if you have any questions, please do contact your sales representative:
Lowe & Co:
- Aaron Nation Mobile: 027 5555 881
- Michael Jones Mobile: 027 826 2750
- Craig Lowe Mobile: 021 764 647
The Wellington Company:
- Rakesh Champaneri Mobile: 021 175 0490
- Avi Champaneri Mobile: 021 342 013