Works onsite at Aro are picking back up after nearly a month and half of delays with various trades due to COVID19. This has unfortunately resulted in our completion dates being pushed out. Stage 1’s revised programme completion is now mid-September, and Stage 2/3 will be delayed by 2 weeks. The teams on site are doing everything possible to make up for lost time and we will keep you updated on progress. Apartmento unfortunately cannot commence yet, with our foundation consent only being issued last month. This was with Wellington City Council for 9 months, and we now await our structural consent (which has been with Council for nearly 60 days). Once we receive this consent, we can get started on Apartmento. Works for the month: April's milestones include the stair installation starting in Stage 1, along with external cladding. Below is a summary of key work on site over the last month.
Stage 1:
- Carpentry and CLT flooring is well underway. Only 1 remaining CLT floor left to install in stage 1.
- External and internal framing is progressing onsite.
- Installation of stairs is complete on 7 units, with the remaining will be completed this week.
- External cladding is progressing, with substrate being installed (note the purple sheets in the image below).
- Roof installation has started this week.
Stage 2b:
- All foundations completed, with the first 7 ground floor slabs poured.
- Level 1 slab formwork is being installed.
Stage 2:
- CLT flooring is due to site this week